A Second Condominium for Hancock
Plans were announce earlier this summer, for a new condo project, to be built just to the east of the Portage Lake Lift Bridge, and just west of the Houghton County Marina.

Click picture to enlarge.
June saw continued work on the fourth floor and roof.

Click picture to enlarge.
By the beginning of August, window work began on the west side, and work continued on the east side balconies.

Click picture to enlarge.
The beginning of August saw the roof work completed, and windows in on the west side of the building. Work then came to a halt for the rest of the month.
         
     
         
PREVIOUSLY ...

Click picture to enlarge.
February 2007, and a relatively light winter, saw the near completion of the fourth floor, additional steel work started, and the closing in of the building.

Click picture to enlarge.
March 2007 saw continuing outside work, and more work being done inside.

Click picture to enlarge.
Late April 2007 saw further outside work, with roof work and balconies being constructed.
         
 
Click picture to enlarge.
The first part of May 2007 saw further roofing work being finished, with inside walls and other work ongoing.

Click picture to enlarge.
With the use of precast concrete panels, construction in December quickened.
         

Click picture to enlarge.
Weather not seen in many years in December, continues to favor construction, as the second floor goes up and the third is started.

Click picture to enlarge.
Christmas brought continued good weather, as the third floor is now well underway.

Click picture to enlarge.
By the second week of December, precast concrete panels are arriving, and
being placed into position, to speed
construction, and add soundproofing to the building.
         

Click picture to enlarge.
Mid October saw the walls go up for what will be the enclosed lower level parking garage.

Click picture to enlarge.
Early November brought further work on the ground floor garage.

Click picture to enlarge.
Later November saw further work on the lower level, while the second story construction begins.

Click picture to enlarge.
This is a view of the project site.

Click picture to enlarge.
The project, which will owned and built by Moyle Construction, Inc., of Houghton, will look as this architectural concept drawing shows.

Click picture to enlarge.
Work in late October continues on the first floor, with upper floor preparations getting under way.

Click picture to enlarge.
As mid September comes, the building pilars are taking shape.

Click picture to enlarge.
The project, which will owned and built by Moyle Construction, Inc., of Houghton, will look as this architectural concept drawing shows.

Click picture to enlarge.
Work began in August, 2006. The ground floor will consist of enclosed parking for the 20 or so tenants.
[ Photos: Roland Burgan; drawing courtesy of City of Hancock, & Moyle Construction, Inc.].  